Future Projects :
MMI HOSPITAL : the first project on completion will have a 332-bed availability and will be fully air-conditioned with multi disciplinary facilities designed TO MEET JCIA STANDARDS
NURSING SCHOOL : the second project would further enhance the quality of healthcare
MEDICAL UNIVERSITY : the third project will providemedical education of international standard
RESEARCH INSTITUTE : the fourth and final project planned will lay a foundation for medical research to further improve the quality of services.
Services Plan For 2011
FIRST QTR 2011 |
STATUS |
|
| ER (Emergency) |
Functional with 11 Beds & 2 Trauma Rooms |
Achieved |
| ICU |
4 Beds ICU in ER |
Achieved |
| 2 nd Operation Theater |
IN Emergency |
Achieved |
| Recovery Room |
4 Beds Recovery in ER |
Achieved |
| Pediatric Ward |
14 Beds |
Deferred to 2 nd QTR |
| 1 st Floor General Ward |
30 Beds |
Achieved |
| SECOND QTR 2011 |
STATUS |
|
| Radiology |
CT Scan |
Achieved |
| Dialysis Unit |
4 Beds Dialysis Unit |
Achieved |
| Pediatric Ward |
14 Beds Pediatric Ward |
Achieved |
| 1 st Floor Special Care |
4 Beds |
Achieved |
| THIRD TO FOURTH QTR 2011 |
STATUS |
|
| Operation Theater Complex |
2 nd Floor 3 OT`s |
In Progress |
| Recovery Room |
2 nd Floor 5 Beds |
In Progress |
| PVT/ Semi PVT Wing |
26 Beds |
Ready for Commissioning |
| General Ward |
Additional 30 Beds |
In Progress |
| Isolation Room |
1 st Floor |
In Progress |
| Pediatric HDU |
5 Beds, 2 Cots |
In Progress |